How long does a building permit take in Boca Raton?

As of November 2026, a new-home permit in Boca Raton takes a median 122 days from application to issue, across the 60 permits issued in the last six months. The middle half took 72 to 148 days, 20 days faster than the six months before (142 days). 52 applications are waiting on the city now, a median 55 days so far.

122 daysmedian, application to permit, for the 60 permits issued in the last six months
72–148days: the middle half of those permits
52new-home applications in review now
55 daysmedian wait so far for those applications; 6 past six months
Month by month

Application to permit, by the month it was issued.

Each row is one month: the permits Boca Raton issued then, each timed from the day its application was filed. The band is the middle half of those permits; a month with fewer than three shows its count alone.

Dec 20255 permitsMiddle half 121 to 268 days.
218 days
Jan 20267 permitsMiddle half 92 to 286 days.
197 days
Feb 20265 permitsMiddle half 58 to 223 days.
105 days
Mar 20263 permitsMiddle half 128 to 164 days.
162 days
Apr 20267 permitsMiddle half 107 to 371 days.
144 days
May 20264 permitsMiddle half 64 to 298 days.
99 days
Jun 202620 permitsMiddle half 101 to 152 days.
122 days
Jul 202613 permitsMiddle half 82 to 141 days.
140 days
Aug 20267 permitsMiddle half 36 to 126 days.
52 days
Sep 20265 permitsMiddle half 86 to 235 days.
155 days
Oct 20269 permitsMiddle half 50 to 175 days.
100 days
Nov 20264 permitsMiddle half 48 to 130 days.
76 days
  • Middle half of that month’s permits
  • Median
Stage by stage

From application to certificate of occupancy.

Each step, for the homes that finished it in the last year. Plan review runs from the application to the permit; the build starts once the city issues it.

How long the whole build takes →
Plan review92 homesMiddle half 80 to 164 days.
123 days
Permit to foundation85 homesMiddle half 22 to 84 days.
36 days
Foundation to walls68 homesMiddle half 25 to 56 days.
41 days
Walls to finishes77 homesMiddle half 125 to 267 days.
189 days
Finishes to certificate of occupancy78 homesMiddle half 223 to 469 days.
304 days
  • Middle half of homes
  • Median
In review now

52 applications waiting on the city.

New-home applications Boca Raton hasn’t issued yet, with nothing built. Half have waited longer than 55 days; 6 have waited more than six months. Applications with no city record for a year are left out as quiet.

See them →
Who reviews the plans

The city’s review, or a private provider’s.

In Florida a builder can hire a licensed private provider to review the plans and inspect the work (Florida Statutes 553.791); the city still issues the permit. Permits issued in the last year, by who reviewed them.

The city’s review125 days

Median from application to permit across 59 permits; the middle half took 91 to 197 days.

A private provider’s review59 days

Median from application to permit across 13 permits; the middle half took 38 to 124 days.

City by city

Permit times where we track them.

Compare the cities →
CityApplication to permitIn review nowWaiting so far
Fort Lauderdale—118102 days
Pompano Beach144 days (9)20163 days
Boca Raton122 days (60)5255 days
Delray Beach127 days (47)4978 days

Application to permit: the median for permits issued in the last six months, with how many. A dash where a city’s records don’t say when its permits were issued.

How long the build takes

From the permit to the certificate of occupancy, stage by stage and by builder: how long it takes to build in Boca Raton.

What it costs

Build cost per square foot, what lots sell for, and two houses priced out: the cost to build in Boca Raton.

Planning a build

Get a lot report for any address, then match builders who have built where you want to.

How it’s measured: new houses, duplexes and townhouse units with their own permit, from the day the new-home permit application was filed to the day the city issued the permit. A gap of more than three years is left out as a renewal or a revived application. Stage dates are the first inspection the city recorded for each stage. Figures as of November 2026, from Boca eHub. How the data works.