How long does it take to build a house in Fort Lauderdale?

As of November 2026, a new house in Fort Lauderdale takes a median 28 months from permit to certificate of occupancy, across 175 houses permitted from 2021 through 2023. The middle half take 23 to 37 months. On the water the median is 33 months; inland, 24.

28.3 momedian build, permit to certificate of occupancy (175 houses)
23–37months: the middle half of builds
33.1 moon the water (95 houses; middle half 27–40 months)
24.4 moinland (80 houses; middle half 19–31 months)
Stage by stage

Where the months go.

Builders file documents with the city as each stage passes inspection. From the permit application, the first foundation document comes at a median 10 months. The block walls go up about 2 months later, the finishes start at about 25 months, and the certificate of occupancy follows about 3 months later. The longest stretch runs from the walls to the finishes: about 14 months.

How stages are read →

When each stage starts

Months after the permit
Foundation154 housesMiddle half 6.9 to 12.8 months.
9.6 mo
Going vertical62 housesMiddle half 8.5 to 24.7 months.
11.5 mo
Finishes157 housesMiddle half 20.2 to 34.8 months.
25.1 mo
Certificate of occupancy175 housesMiddle half 23 to 37.2 months.
28.3 mo
  • Middle half of houses in Fort Lauderdale
  • Median

On the water and inland

Median months after the permit
Foundation9.1 mo inland · 10.1 mo on the water
+1.0
Going vertical10.6 mo inland · 11.7 mo on the water
+1.1
Finishes21.8 mo inland · 29.4 mo on the water
+7.6
Certificate of occupancy24.4 mo inland · 33.1 mo on the water
+8.8
  • On the water
  • Inland

Both sides of the water reach the foundation at about 10 months. The gap opens after that: the finishes start at 29.4 months on the water and 21.8 inland.

By size and type

The biggest houses take the longest.

Houses of 7,000 sq ft and up took a median 33.2 months, against 21.6 to 26.2 for smaller ones; 46 of those 49 are on the water. Townhome and villa-pair units are measured the same way, one unit at a time.

Townhomes rising now →

Permit to certificate of occupancy

Months
Under 3,500 sq ft15 houses · none on the waterMiddle half 22.9 to 31.2 months.
26.2 mo
3,500–5,000 sq ft40 houses · 9 on the waterMiddle half 17.3 to 25.7 months.
21.6 mo
5,000–7,000 sq ft39 houses · 20 on the waterMiddle half 22 to 34.7 months.
24.8 mo
7,000 sq ft and up49 houses · 46 on the waterMiddle half 26.8 to 37.7 months.
33.2 mo
Townhome unit51 unitsMiddle half 20.7 to 25.7 months.
23.0 mo
Villa-pair unit41 unitsMiddle half 18.6 to 32.6 months.
23.7 mo
  • Middle half in Fort Lauderdale
  • Median

Home size is the tax roll’s total building area, garage and covered areas included, so it runs larger than the area under air.

A townhome unit is one of three or more attached homes, each on its own lot; a villa pair is two. Each unit has its own permit and certificate of occupancy, so each is timed on its own. How townhomes are tracked.

By builder

The fastest and slowest builders, on the record.

All 9 builders with 5 or more finished homes in Fort Lauderdale to time, fastest first. Each is set against homes like theirs, as on their own page: waterfront homes for builders mostly on the water, inland homes for those mostly inland, since waterfront builds run longer.

Compare every builder →
Sloan Consulting30 homes timed · all inlandAgainst inland homes: median 24.4 months.
13.2 mo
Citadel Property Construction5 homes timed · mostly inlandAgainst inland homes: median 24.4 months.
13.3 mo
SDG Services7 homes timed · all inlandAgainst inland homes: median 24.4 months.
14.8 mo
SCD Developments5 homes timed · all inlandAgainst inland homes: median 24.4 months.
15.5 mo
Zachary Rose General Contractor6 homes timed · mostly inlandAgainst inland homes: median 24.4 months.
18.2 mo
ACD Inst Corp14 homes timed · mostly inlandAgainst inland homes: median 24.4 months.
19.8 mo
ML Construction Group5 homes timed · mostly inlandAgainst inland homes: median 24.4 months.
24.3 mo
Gulf Building12 homes timed · mostly on the waterAgainst waterfront homes: median 33.1 months.
31.6 mo
Double P Construction6 homes timed · mostly on the waterAgainst waterfront homes: median 33.1 months.
34.5 mo
  • Builder’s median
  • Middle half, homes like theirs in Fort Lauderdale
  • Median, homes like theirs

A builder’s median covers every finished home of theirs in Fort Lauderdale with both dates on record, whatever year it was permitted.

What stretches a timeline

What the slower builds have in common.

Comparisons across the same 175 houses. They show which builds ran longer, not why.

On the water+8.7 mo

Waterfront houses took a median 33.1 months, inland ones 24.4. The difference builds up after the walls: the finishes start at 29.4 months on the water and 21.8 inland.

Size33.2 mo

Houses of 7,000 sq ft and up, against 21.6 to 26.2 months for smaller ones. 46 of those 49 are on the water.

Stories34.1 mo

Houses of three stories or more, going by the permit’s plans. Two-story houses took a median 28.9 months; one-story houses, 24.4.

Custom builds+6.7 mo

Custom houses took a median 31.1 months; likely spec houses, built to sell, 24.4. On the water that’s 33.1 against 33.2; inland, 26.1 against 23.5. What the labels mean.

Before the foundation9.6 mo

From the permit application to the first foundation document, on the water and inland alike. The clock starts at the application, so this includes the city’s review of the plans: how long that review is taking now.

Not finished yet107

Of the 471 houses permitted 2021–2023, 83 are still being built and 20 have gone quiet; 4 are still waiting on their permit. They can’t be timed until they finish, so the medians here lean fast.

Rising now

345 homes are rising in Fort Lauderdale; 251 show an estimated completion window worked out from these numbers. The most are in Coral Ridge, Victoria Park and Rio Vista.

What it costs

Estimated build cost per square foot, what lots sell for, and two houses priced out: the cost to build in Fort Lauderdale.

Planning a build

Find a lot with a lot report for any address, check how long permits are taking, then match builders who have built where you want to, or compare cities.

How it’s measured: from the new-home permit application to the first certificate-of-occupancy packet submitted to the city, for the 175 houses permitted 2021–2023 with both dates on record (471 were permitted in those years). Stage dates are the first document the city recorded for each stage. Figures as of November 2026, from LauderBuild and the county parcel roll. How the data works.