How long does it take to build a house in Delray Beach?

As of November 2026, a new house in Delray Beach takes a median 20 months from permit to certificate of occupancy, across 388 houses permitted from 2021 through 2023. The middle half take 14 to 24 months. On the water the median is 26 months; inland, 19.

19.6 momedian build, permit to certificate of occupancy (388 houses)
14–24months: the middle half of builds
25.9 moon the water (36 houses; middle half 21–31 months)
19.0 moinland (352 houses; middle half 14–23 months)
Stage by stage

Where the months go.

The city logs each inspection as the work passes it. From the permit application, the first foundation inspection comes at a median 7 months. The block walls go up about 1 month later, the finishes start at about 13 months, and the certificate of occupancy follows about 6 months later. The longest stretch runs from the permit to the foundation: about 7 months.

How stages are read →

When each stage starts

Months after the permit
Foundation346 housesMiddle half 4.5 to 9.6 months.
6.5 mo
Going vertical348 housesMiddle half 5.6 to 10.6 months.
7.8 mo
Finishes371 housesMiddle half 9.9 to 16.8 months.
13.5 mo
Certificate of occupancy388 housesMiddle half 14.1 to 24.1 months.
19.6 mo
  • Middle half of houses in Delray Beach
  • Median

On the water and inland

Median months after the permit
Foundation6.3 mo inland · 7.2 mo on the water
+0.8
Going vertical7.8 mo inland · 8.6 mo on the water
+0.9
Finishes12.9 mo inland · 15.6 mo on the water
+2.6
Certificate of occupancy19.0 mo inland · 25.9 mo on the water
+6.9
  • On the water
  • Inland

Both sides of the water reach the foundation at about 7 months. The gap opens after that: the finishes start at 15.6 months on the water and 12.9 inland.

By size and type

The biggest houses take the longest.

Houses of 7,000 sq ft and up took a median 25.9 months, against 16.1 to 22.9 for smaller ones; 3 of those 7 are on the water.

Permit to certificate of occupancy

Months
Under 3,500 sq ft200 houses · 2 on the waterMiddle half 12.2 to 20.5 months.
16.1 mo
3,500–5,000 sq ft109 houses · 6 on the waterMiddle half 17.5 to 25.8 months.
21.9 mo
5,000–7,000 sq ft47 houses · 19 on the waterMiddle half 20 to 28.4 months.
22.9 mo
7,000 sq ft and up7 houses · 3 on the waterMiddle half 25.2 to 28.3 months.
25.9 mo
  • Middle half in Delray Beach
  • Median

Home size is the tax roll’s total building area, garage and covered areas included, so it runs larger than the area under air.

By builder

The fastest and slowest builders, on the record.

The fastest and slowest of the 27 builders with 5 or more finished homes in Delray Beach to time, fastest first. Each is set against homes like theirs, as on their own page: waterfront homes for builders mostly on the water, inland homes for those mostly inland, since waterfront builds run longer.

Compare every builder →
Toll Bros6 homes timed · all inlandAgainst inland homes: median 19 months.
12.0 mo
Richbuilt Sons7 homes timed · all inlandAgainst inland homes: median 19 months.
12.2 mo
Tropical Custom Builders12 homes timed · all inlandAgainst inland homes: median 19 months.
12.3 mo
Lennar Homes39 homes timed · all inlandAgainst inland homes: median 19 months.
12.5 mo
J & M Contractors of South Florida7 homes timed · all inlandAgainst inland homes: median 19 months.
12.6 mo
SDGC6 homes timed · mostly inlandAgainst inland homes: median 19 months.
24.1 mo
Beachfront Builders7 homes timed · mostly on the waterAgainst waterfront homes: median 25.9 months.
24.4 mo
Seagate Capital Construction5 homes timed · mostly inlandAgainst inland homes: median 19 months.
25.6 mo
Shoreline Building Group7 homes timed · all inlandAgainst inland homes: median 19 months.
33.1 mo
Rapcon5 homes timed · all inlandAgainst inland homes: median 19 months.
43.7 mo
  • Builder’s median
  • Middle half, homes like theirs in Delray Beach
  • Median, homes like theirs

A builder’s median covers every finished home of theirs in Delray Beach with both dates on record, whatever year it was permitted.

What stretches a timeline

What the slower builds have in common.

Comparisons across the same 388 houses. They show which builds ran longer, not why.

On the water+6.9 mo

Waterfront houses took a median 25.9 months, inland ones 19.0. The difference builds up after the walls: the finishes start at 15.6 months on the water and 12.9 inland.

Size25.9 mo

Houses of 7,000 sq ft and up, against 16.1 to 22.9 months for smaller ones. 3 of those 7 are on the water.

Custom builds+4.0 mo

Custom houses took a median 21.6 months; likely spec houses, built to sell, 17.6. On the water that’s 28.2 against 20.6; inland, 20.4 against 17.5. What the labels mean.

Before the foundation6.5 mo

From the permit application to the first foundation document, on the water and inland alike. The clock starts at the application, so this includes the city’s review of the plans: how long that review is taking now.

Not finished yet22

Of the 412 houses permitted 2021–2023, 11 are still being built and 11 have gone quiet. They can’t be timed until they finish, so the medians here lean fast.

Rising now

103 homes are rising in Delray Beach; 85 show an estimated completion window worked out from these numbers. The most are in Layton Pointe, Osceola Park and Plumosa Park.

What it costs

Estimated build cost per square foot, what lots sell for, and two houses priced out: the cost to build in Delray Beach.

Planning a build

Find a lot with a lot report for any address, check how long permits are taking, then match builders who have built where you want to, or compare cities.

How it’s measured: from the new-home permit application to the first certificate-of-occupancy packet submitted to the city, for the 388 houses permitted 2021–2023 with both dates on record (412 were permitted in those years). Stage dates are the first document the city recorded for each stage. Figures as of November 2026, from Delray Beach eServices and the county parcel roll. How the data works.