Permit times · updated daily

How long building permits take, city by city.

New-home permits from application to issue, the applications waiting on each city now, and how soon building starts once the permit is issued. Figures as of November 2026, updated every day.

Application to permit

Permits issued in the last six months
Fort Lauderdaleno issue dates in its records
—
Pompano Beach9 permitsMiddle half 125 to 333 days.
144 days
Boca Raton60 permitsMiddle half 72 to 148 days.
122 days
Delray Beach47 permitsMiddle half 76 to 250 days.
127 days
  • Middle half of the city’s permits
  • Median
Side by side

Waiting now, and the start of the build.

Medians in days. Plan review and the start of the build are for homes that reached them in the last year. Each city’s page goes on, stage by stage, to the certificate of occupancy.

CityIn review nowWaiting so farPlan review, last yearPermit to foundation
Fort Lauderdale118102——
Pompano Beach2016319148
Boca Raton525512336
Delray Beach497812728

A dash where a city’s records don’t say when its permits were issued, or too few homes reached a step to give a median. The later stages aren’t compared here, since each city’s records mark them differently. How permit times are measured.