How long does a building permit take in Pompano Beach?

As of October 2026, a new-home permit in Pompano Beach takes a median 144 days from application to issue, across the 9 permits issued in the last six months. The middle half took 125 to 333 days, 99 days faster than the six months before (243 days). 20 applications are waiting on the city now, a median 163 days so far.

144 daysmedian, application to permit, for the 9 permits issued in the last six months
125–333days: the middle half of those permits
20new-home applications in review now
163 daysmedian wait so far for those applications; 9 past six months
Month by month

Application to permit, by the month it was issued.

Each row is one month: the permits Pompano Beach issued then, each timed from the day its application was filed. The band is the middle half of those permits; a month with fewer than three shows its count alone.

Nov 20253 permitsMiddle half 172 to 172 days.
172 days
Dec 20251 permit
—
Jan 20263 permitsMiddle half 191 to 978 days.
357 days
Apr 20263 permitsMiddle half 197 to 306 days.
288 days
May 20261 permit
—
Jun 20264 permitsMiddle half 124 to 692 days.
218 days
Aug 20261 permit
—
Sep 20263 permitsMiddle half 130 to 364 days.
170 days
  • Middle half of that month’s permits
  • Median
Stage by stage

From application to certificate of occupancy.

Each step, for the homes that finished it in the last year. Plan review runs from the application to the permit; the build starts once the city issues it.

How long the whole build takes →
Plan review19 homesMiddle half 144 to 357 days.
191 days
Permit to foundation18 homesMiddle half 39 to 65 days.
48 days
Foundation to walls46 homesMiddle half 18 to 90 days.
48 days
Walls to finishes51 homesMiddle half 18 to 70 days.
38 days
Finishes to certificate of occupancy57 homesMiddle half 39 to 192 days.
71 days
  • Middle half of homes
  • Median
In review now

20 applications waiting on the city.

New-home applications Pompano Beach hasn’t issued yet, with nothing built. Half have waited longer than 163 days; 9 have waited more than six months. Applications with no city record for a year are left out as quiet.

See them →
City by city

Permit times where we track them.

Compare the cities →
CityApplication to permitIn review nowWaiting so far
Fort Lauderdale—118102 days
Pompano Beach144 days (9)20163 days
Boca Raton122 days (60)5255 days
Delray Beach127 days (47)4978 days

Application to permit: the median for permits issued in the last six months, with how many. A dash where a city’s records don’t say when its permits were issued.

How long the build takes

From the permit to the certificate of occupancy, stage by stage and by builder: how long it takes to build in Pompano Beach.

What it costs

Build cost per square foot, what lots sell for, and two houses priced out: the cost to build in Pompano Beach.

Planning a build

Get a lot report for any address, then match builders who have built where you want to.

How it’s measured: new houses, duplexes and townhouse units with their own permit, from the day the new-home permit application was filed to the day the city issued the permit. A gap of more than three years is left out as a renewal or a revived application. Stage dates are the first inspection the city recorded for each stage. Figures as of October 2026, from Pompano Beach Click2Gov. How the data works.