How long does a building permit take in Delray Beach?

As of November 2026, a new-home permit in Delray Beach takes a median 127 days from application to issue, across the 47 permits issued in the last six months. The middle half took 76 to 250 days, about the same as the six months before (127 days). 49 applications are waiting on the city now, a median 78 days so far.

127 daysmedian, application to permit, for the 47 permits issued in the last six months
76–250days: the middle half of those permits
49new-home applications in review now
78 daysmedian wait so far for those applications; 13 past six months
Month by month

Application to permit, by the month it was issued.

Each row is one month: the permits Delray Beach issued then, each timed from the day its application was filed. The band is the middle half of those permits; a month with fewer than three shows its count alone.

Dec 20251 permit
—
Jan 20264 permitsMiddle half 94 to 211 days.
139 days
Feb 20267 permitsMiddle half 70 to 198 days.
124 days
Mar 20263 permitsMiddle half 43 to 171 days.
154 days
Apr 202610 permitsMiddle half 127 to 202 days.
161 days
May 20269 permitsMiddle half 91 to 163 days.
122 days
Jun 202610 permitsMiddle half 63 to 140 days.
81 days
Jul 202612 permitsMiddle half 62 to 264 days.
132 days
Aug 202610 permitsMiddle half 62 to 259 days.
125 days
Sep 20264 permitsMiddle half 156 to 428 days.
409 days
Oct 20264 permitsMiddle half 48 to 823 days.
138 days
Nov 20262 permits
—
  • Middle half of that month’s permits
  • Median
Stage by stage

From application to certificate of occupancy.

Each step, for the homes that finished it in the last year. Plan review runs from the application to the permit; the build starts once the city issues it.

How long the whole build takes →
Plan review80 homesMiddle half 82 to 192 days.
127 days
Permit to foundation73 homesMiddle half 17 to 45 days.
28 days
Foundation to walls72 homesMiddle half 14 to 37 days.
23 days
Walls to finishes56 homesMiddle half 78 to 266 days.
154 days
Finishes to certificate of occupancy79 homesMiddle half 146 to 311 days.
229 days
  • Middle half of homes
  • Median
In review now

49 applications waiting on the city.

New-home applications Delray Beach hasn’t issued yet, with nothing built. Half have waited longer than 78 days; 13 have waited more than six months, the longest 15 months. Applications with no city record for a year are left out as quiet.

See them →
Who reviews the plans

The city’s review, or a private provider’s.

In Florida a builder can hire a licensed private provider to review the plans and inspect the work (Florida Statutes 553.791); the city still issues the permit. Permits issued in the last year, by who reviewed them.

The city’s review169 days

Median from application to permit across 44 permits; the middle half took 126 to 267 days.

A private provider’s review86 days

Median from application to permit across 34 permits; the middle half took 67 to 131 days.

City by city

Permit times where we track them.

Compare the cities →
CityApplication to permitIn review nowWaiting so far
Fort Lauderdale—118102 days
Pompano Beach144 days (9)20163 days
Boca Raton122 days (60)5255 days
Delray Beach127 days (47)4978 days

Application to permit: the median for permits issued in the last six months, with how many. A dash where a city’s records don’t say when its permits were issued.

How long the build takes

From the permit to the certificate of occupancy, stage by stage and by builder: how long it takes to build in Delray Beach.

What it costs

Build cost per square foot, what lots sell for, and two houses priced out: the cost to build in Delray Beach.

Planning a build

Get a lot report for any address, then match builders who have built where you want to.

How it’s measured: new houses, duplexes and townhouse units with their own permit, from the day the new-home permit application was filed to the day the city issued the permit. A gap of more than three years is left out as a renewal or a revived application. Stage dates are the first inspection the city recorded for each stage. Figures as of November 2026, from Delray Beach eServices. How the data works.