Complete

Complete: certificate-of-occupancy packet submitted, or on the tax roll as a built home

Likely spec

Likely spec: owned by a company named for the builder. Not confirmed by the builder.

1867 NW 6 Pl

1867 NW 6 Pl in January 20261867 NW 6 Pl in January 20252025 · Broward County · Broward Co.2026 · Broward County · Broward Co.

Drag to compare the lot in January 2025 with January 2026. The pink line is the surveyed parcel boundary.

Where it stands

Last city record Mar 12, 2026
CompletedMar 2026Sales on record through Jun 2026

The numbers

From deeds, the permit and the parcel roll
Lot purchase
Part of a $1.48M purchase of 64 lots, Oct 2023
Lot size
4,576 sf 0.11 acres
Declared permit value
$381K as declared; real cost runs well higher
Home size
~3,018 sf from the permit’s plans
Plan
Not in the permit
Flood zone
X
Waterfront
No
Ownership
Company-owned lot likely spec: owned by a company named for the builder

Against the market

Pompano Beach · since 2021
Build time, months from permit
0 mo30 mo60 mo

Built in 9.4 months, 8.7 months faster than typical (18.1 months for homes off the water in Pompano Beach).

  • This home
  • Middle half, Pompano Beach off the water

    144 homes off the water in Pompano Beach permitted 2021–2023, from the permit application to the certificate-of-occupancy packet.

  • Median
How we calculate this

Construction log

55 city records
  1. Fence/wall finalApproved
  2. Building finalApproved
  3. Zoning finalApproved
  4. Final-plumbingApproved
  5. Final landscapeApproved
  6. Final floodplainApproved
  7. Final boundary/topo surveyApproved
  8. Final-mechanicalApproved
  9. Electrical final-electricApproved
  10. Roof: truss drawings filedTruss · Approved
  11. Tie beamsApproved
  12. Soil treatmentApproved
  13. Soil compactionApproved
  14. Slab/reinforcingApproved
  15. Roof sheathingApproved
  16. Miscellaneous finalApproved
  17. LathApproved
  18. FramingApproved
  19. FootingsApproved
  20. Final-plumbingApproved
  21. Fenestration finalApproved
  22. Engineering paver limerock base insp.Approved
  23. Engineering paver block final inspectionApproved
  24. Addition finalApproved
  25. In-prog equipment elevationApproved
  26. In-prog elevation certificateApproved
  27. In-prog boundry surveyApproved
  28. Finished elevation certificateApproved
  29. Electrical 30 day temporary powerApproved
  30. Plumbing lawn sprinklerApproved
  31. Tin tagApproved
  32. Tile/shingle-in progressApproved
  33. New roof finalApproved
  34. Drywall-screw/nailApproved
  35. LathApproved
  36. Finishes: insulation certifiedInsulation-walls · Approved
  37. Finishes: insulation certifiedInsulation-ceilings · Approved
  38. FramingApproved
  39. Electrical underground wiring/pipingApproved
  40. Electrical service roughApproved
  41. Electrical roughApproved
  42. Electrical foundation groundApproved
  43. Plumbing top outApproved
  44. Windows/doorsApproved
  45. Mechanical roughApproved
  46. Roof: truss drawings filedTruss · Approved
  47. Roof sheathingApproved
  48. Tie beamsApproved
  49. Slab/reinforcingApproved
  50. FootingsApproved
  51. Columns/shear wallApproved
  52. Soil treatmentPartially approved
  53. Soil compactionPartially approved
  54. Plumbing roughApproved
  55. New-home permit filedResidential New Construction Permit · CO issued

Permit 25-00004404 on Pompano Beach Click2Gov: “NEW SFR”

Nearby

More new homes nearby

All 97 in Old Collier →

Also close by: 1883 NW 7 St · 1875 NW 7 St · 671 NW 18 Mnr · 1867 NW 7 St · 1849 NW 6 Pl · 660 NW 18 Mnr