670 NW 18 Mnr
Drag to compare the lot in January 2025 with January 2026. The pink line is the surveyed parcel boundary.
Where it stands
Last city record Jan 29, 2026PermitMay ’25
FoundationAug ’25
VerticalSep ’25
FinishDec ’25
COJan ’26
DoneJan ’26
CompletedJan 2026Sales on record through Jun 2026
The numbers
From deeds, the permit and the parcel roll- Lot purchase
- Part of a $1.48M purchase of 64 lots, Oct 2023
- Lot size
- 4,865 sf 0.11 acres
- Declared permit value
- $336K as declared; real cost runs well higher
- Home size
- ~2,627 sf from the permit’s plans
- Plan
- Not in the permit
- Flood zone
- X
- Waterfront
- No
- Ownership
- Company-owned lot likely spec: owned by a company named for the builder
Against the market
Pompano Beach · since 2021Build time, months from permit
0 mo30 mo60 mo
Built in 8.9 months, 9.2 months faster than typical (18.1 months for homes off the water in Pompano Beach).
- This home
Middle half, Pompano Beach off the water
144 homes off the water in Pompano Beach permitted 2021–2023, from the permit application to the certificate-of-occupancy packet.
- Median
Construction log
53 city records- Zoning finalApproved
- Plumbing lawn sprinklerApproved
- New roof finalApproved
- Final-plumbingApproved
- Fenestration finalApproved
- Building finalApproved
- Final landscapeApproved
- Windows/doorsApproved
- Wall sheathingApproved
- Roof: truss drawings filedTruss · Approved
- Tie beamsApproved
- Soil treatmentApproved
- Soil compactionApproved
- Slab/reinforcingApproved
- Shutter final inspectionApproved
- Roof sheathingApproved
- LathApproved
- Finishes: insulation certifiedInsulation-walls · Approved
- Finishes: insulation certifiedInsulation-ceilings · Approved
- FramingApproved
- FootingsApproved
- Drywall-screw/nailApproved
- Columns/shear wallApproved
- Tie beamsApproved
- Soil treatmentApproved
- Soil compactionApproved
- Slab/reinforcingApproved
- Roof sheathingApproved
- Miscellaneous finalApproved
- LathApproved
- FramingApproved
- FootingsApproved
- Final-plumbingApproved
- Final-mechanicalApproved
- Engineering paver limerock base insp.Approved
- Engineering paver block final inspectionApproved
- Electrical final-electricApproved
- Columns/shear wallApproved
- In-prog equipment elevationApproved
- In-prog elevation certificateApproved
- Finished elevation certificateApproved
- Final floodplainApproved
- Final boundary/topo surveyApproved
- Electrical 30 day temporary powerApproved
- Tin tagApproved
- Mop - in progressApproved
- Plumbing top outApproved
- Electrical roughApproved
- Plumbing roughApproved
- Mechanical roughApproved
- In-prog boundry surveyApproved
- Electrical foundation groundApproved
- New-home permit filedResidential New Construction Permit · CO issued
Permit 25-00003575 on Pompano Beach Click2Gov: “NEW TWO STRY SFR 4/3”
Nearby
All 97 in Old Collier →More new homes nearby
Complete
671 NW 18 Mnr
Old CollierD R Horton
Permit
Foundation
Vertical
Finish
CO
Done
Lot bought—
Plan~3,303 sf
Declared permit value$153K
Complete
660 NW 18 Mnr
Old CollierD R Horton
Permit
Foundation
Vertical
Finish
CO
Done
Lot bought—
Plan~3,303 sf
Declared permit value$411K
Complete
661 NW 18 Mnr
Old CollierD R Horton
Permit
Foundation
Vertical
Finish
CO
Done
Lot bought—
Plan~3,018 sf
Declared permit value$376K