Builder · permits 2022–2025
Taber Construction
3houses2cities
3 new homes since 2022: 2 in Fort Lauderdale, 1 in Pompano Beach. 1 on the water, mostly in Rio Vista and Santa Barbara Shores. State license CGC1534681.
Where they build
City by city, each against its own typical build
New homes3
1 complete · 2 rising
On the water1
33% of their homes · rank 144 overall
Typical build17.2 mo
Only 1 finished home to measure
Top recorded sale—
No finished-home sale on record
Rising now
2 homes in progress
RisingWaterfront
2651 SE 10 Ct
Santa Barbara Shores, Pompano BeachTaber Construction
Permit
Foundation
Vertical
Finish
CO
Done
Lot bought$1.94M
Plan~4,931 sf
Est. doneNov ’26–Apr ’28
Rising
828 SE 9 St
Rio Vista, Fort LauderdaleTaber Construction
Permit
Foundation
Vertical
Finish
CO
Done
Lot bought—
Plan3 bd · 3.5 ba
Est. doneMar–Dec ’27
Against the market
Each city · homes since 2021Build time in Fort Lauderdale (1 finished home)
0 mo30 mo60 mo
Their median in Fort Lauderdale is 17.2 months; the median for homes off the water in Fort Lauderdale is 24.4. Small sample, so read it loosely.
Median declared permit value $970K per home, the 71st highest among 188 builders with three or more homes. Declared values run well below real construction cost.
Their lots cost a median $1.29M.
- Their median
Middle half, each city off the water
80 homes off the water in Fort Lauderdale permitted 2021–2023, from the permit application to the certificate-of-occupancy packet.
- Median
Every new home on record
Portfolio
| Address | City | Neighborhood | Permit | Status | Lot | Declared permit value | Sale |
|---|---|---|---|---|---|---|---|
| 828 SE 9 St | Fort Lauderdale | Rio Vista | May 2025 | Rising | — | $970K | — |
| 2651 SE 10 CtWater | Pompano Beach | Santa Barbara Shores | Nov 2024 | Rising | $1.94M | $2.81M | — |
| 812 SE 9 St | Fort Lauderdale | Rio Vista | Nov 2022 | Complete | $650K | $407K | — |