Complete
Complete: certificate-of-occupancy packet submitted, or on the tax roll as a built home
Likely spec
Likely spec: owned by a company named for the builder. Not confirmed by the builder.
651 NW 18 Mnr
Drag to compare the lot in January 2025 with January 2026. The pink line is the surveyed parcel boundary.
Where it stands
Last city record Mar 10, 2026PermitJun ’25
FoundationOct ’25
VerticalNov ’25
FinishDec ’25
COMar ’26
DoneMar ’26
CompletedMar 2026Sales on record through Jun 2026
The numbers
From deeds, the permit and the parcel roll- Lot purchase
- Part of a $1.48M purchase of 64 lots, Oct 2023
- Lot size
- 4,500 sf 0.10 acres
- Declared permit value
- $271K as declared; real cost runs well higher
- Home size
- ~2,046 sf from the permit’s plans
- Plan
- Not in the permit
- Flood zone
- X base flood elevation 11 ft
- Waterfront
- No
- Ownership
- Company-owned lot likely spec: owned by a company named for the builder
Against the market
Pompano Beach · since 2021Build time, months from permit
0 mo30 mo60 mo
Built in 9.2 months, 8.9 months faster than typical (18.1 months for homes off the water in Pompano Beach).
- This home
Middle half, Pompano Beach off the water
144 homes off the water in Pompano Beach permitted 2021–2023, from the permit application to the certificate-of-occupancy packet.
- Median
Construction log
45 city records- Final-plumbingApproved
- Building finalApproved
- Zoning finalApproved
- Final landscapeApproved
- Electrical final-electricApproved
- Windows/doorsApproved
- Mechanical roughApproved
- Final-mechanicalApproved
- Roof sheathingApproved
- Finishes: insulation certifiedInsulation-ceilings · Approved
- FurringApproved
- Floor/deck/dock framingApproved
- BeamsApproved
- In-prog equipment elevationApproved
- In-prog boundry surveyApproved
- Finished elevation certificateApproved
- Final floodplainApproved
- Final boundary/topo surveyApproved
- Miscellaneous finalApproved
- Engineering paver block final inspectionApproved
- New roof finalApproved
- Final-plumbingApproved
- Plumbing lawn sprinklerApproved
- Electrical service roughApproved
- Electrical final-electricApproved
- Engineering paver limerock base insp.Approved
- Electrical 30 day temporary powerApproved
- Tile/shingle-in progressApproved
- Drywall-screw/nailApproved
- LathApproved
- Tin tagCancelled
- Finishes: insulation certifiedInsulation-walls · Approved
- FramingApproved
- Plumbing top outApproved
- Electrical roughApproved
- Soil compactionApproved
- Roof: truss drawings filedTruss · Approved
- In-prog elevation certificateApproved
- Columns/shear wallApproved
- Soil treatmentApproved
- Slab/reinforcingApproved
- Electrical underground wiring/pipingApproved
- Electrical foundation groundApproved
- Plumbing roughApproved
- New-home permit filedResidential New Construction Permit · CO issued
Permit 25-00004429 on Pompano Beach Click2Gov: “NEW SFR”
Nearby
All 97 in Old Collier →More new homes nearby
Complete
661 NW 18 Mnr
Old CollierD R Horton
Permit
Foundation
Vertical
Finish
CO
Done
Lot bought—
Plan~3,018 sf
Declared permit value$376K
Complete
641 NW 18 Mnr
Old CollierD R Horton
Permit
Foundation
Vertical
Finish
CO
Done
Lot bought—
Plan~3,303 sf
Declared permit value$316K
Complete
671 NW 18 Mnr
Old CollierD R Horton
Permit
Foundation
Vertical
Finish
CO
Done
Lot bought—
Plan~3,303 sf
Declared permit value$153K
Also close by: 631 NW 18 Mnr · 660 NW 18 Mnr · 670 NW 18 Mnr · 621 NW 18 Mnr · 650 NW 18 Mnr · 611 NW 18 Mnr