Complete

Complete: certificate-of-occupancy packet submitted, or on the tax roll as a built home

Likely spec

Likely spec: owned by a company named for the builder. Not confirmed by the builder.

1842 NW 6 Ct

1842 NW 6 Ct in January 20261842 NW 6 Ct in January 20252025 · Broward County · Broward Co.2026 · Broward County · Broward Co.

Drag to compare the lot in January 2025 with January 2026. The pink line is the surveyed parcel boundary.

Where it stands

Last city record Mar 24, 2026
CompletedMar 2026Sales on record through Jun 2026

The numbers

From deeds, the permit and the parcel roll
Lot purchase
Part of a $1.48M purchase of 64 lots, Oct 2023
Lot size
4,500 sf 0.10 acres
Declared permit value
$258K as declared; real cost runs well higher
Home size
~2,332 sf from the permit’s plans
Plan
Not in the permit
Flood zone
AH base flood elevation 11 ft
Waterfront
No
Ownership
Company-owned lot likely spec: owned by a company named for the builder

Against the market

Pompano Beach · since 2021
Build time, months from permit
0 mo30 mo60 mo

Built in 9.2 months, 8.9 months faster than typical (18.1 months for homes off the water in Pompano Beach).

  • This home
  • Middle half, Pompano Beach off the water

    144 homes off the water in Pompano Beach permitted 2021–2023, from the permit application to the certificate-of-occupancy packet.

  • Median
How we calculate this

Construction log

53 city records
  1. Final surveyApproved
  2. Fenestration finalApproved
  3. Building finalApproved
  4. Zoning finalApproved
  5. Electrical final-electricApproved
  6. Final-plumbingApproved
  7. Windows/doorsApproved
  8. Roof: truss drawings filedTruss · Approved
  9. Tie beamsApproved
  10. Soil treatmentApproved
  11. Soil compactionApproved
  12. Slab/reinforcingApproved
  13. Roof sheathingApproved
  14. Plumbing lawn sprinklerCancelled
  15. Miscellaneous finalApproved
  16. LathApproved
  17. FramingApproved
  18. FootingsApproved
  19. Final-mechanicalApproved
  20. Final landscapeApproved
  21. Columns/shear wallApproved
  22. Blower door test - certificateApproved
  23. In-prog equipment elevationApproved
  24. In-prog elevation certificateApproved
  25. In-prog boundry surveyApproved
  26. Form board surveyApproved
  27. Finished elevation certificateApproved
  28. Final floodplainApproved
  29. Final boundary/topo surveyApproved
  30. Final-plumbingApproved
  31. Engineering paver block final inspectionApproved
  32. Electrical final-electricApproved
  33. Electrical 30 day temporary powerApproved
  34. New roof finalApproved
  35. Engineering paver limerock base insp.Approved
  36. Tin tagApproved
  37. Tile/shingle-in progressApproved
  38. Drywall-screw/nailApproved
  39. LathApproved
  40. Finishes: insulation certifiedInsulation-walls · Approved
  41. Finishes: insulation certifiedInsulation-ceilings · Approved
  42. FramingApproved
  43. Electrical slabApproved
  44. Electrical roughApproved
  45. Electrical foundation groundApproved
  46. Plumbing top outApproved
  47. Mechanical roughApproved
  48. Roof: truss drawings filedTruss · Approved
  49. Roof sheathingApproved
  50. FootingsApproved
  51. Columns/shear wallApproved
  52. Plumbing roughApproved
  53. New-home permit filedResidential New Construction Permit · CO issued

Permit 25-00004934 on Pompano Beach Click2Gov: “NEW ONE STRY SFR 3/2 - NEW SFR 3/2”